SCIGN Site Reconnaissance Progress Log

SCIGN Site Reconnaissance Progress Log

Log maintained by Nancy King (626-583-7815, nking@usgs.gov). Some months are missing, because I was away or busy with other things.

  • August 21-29, 1997
  • September 1997
  • October 1997
  • November 1997

  • January 13-30 1998
  • February 1998
  • March 1998
  • April 1998
  • May 1998
  • June 1998
  • July 1998
  • August 1998
  • November 1998
  • December 23, 1998 (the only entry for December 1998)

  • January 28, 1999 (the only entry for January 1999)
  • February 08, 1999 (the only entry for February 1999)

  • March 04, 1999
  • March 10, 1999
  • March 11, 1999
  • March 30, 1999
  • March 31, 1999

  • April 02, 1999

  • May 20, 1999

  • June 4, 1999

  • SCIGN home page
  • Recon Notes (home page for site recon WWW site)


    August 21, 1997
    Thursday
    Site Recon Meeting
    USGS Pasadena

    Present:

    Yehuda Bock
    John Galetzka
    Nancy King
    Bob Packard
    Bob Reader
    Bill Young

    Bob Packard's report:

    Bill Young's report:

    Bob Reader's report:

    Yehuda Bock's report:

    USGS (Nancy King and John Galetzka) report:


    August 22, 1997
    Friday

    Bob Packard and his son, a senior electrical inspector, will come by USGS-Pasadena next week to discuss how best to prepare the electrical permit. The exact time will be set next week.


    August 25, 1997
    Monday

    Nancy King notified John Scheid of the meeting this week about electrical permits. Scheid plans to attend.

    Will Prescott will do two days of recon, sometime in the next two weeks.

    Yehuda Bock told Nancy King that Scripps will begin active recon in the middle of September. George Liu, a Unavco engineer, will arrive September 8. He will be working with both Scripps and USGS-Pasadena.


    August 26, 1997
    Tuesday

    Bill Young called Nancy King to say

    August 27, 1997
    Wednesday

    Bob Packard will do recon along Profile A tomorrow. Specifically, he will look at:

    Meeting on electrical specs is tentatively set for Thursday at 5 pm.

    Nancy King and John Galetzka presented recon results to the Executive Committee.


    August 28, 1997
    Thursday

    Nancy began to prepare a list of sites for recon by Will Prescott on Friday.

    Meeting on electrical specs:

    Bob Packard reported on his recon along Profile A:


    August 29, 1997
    Friday

    Mike Duffy (Metropolitan Water District) left voice mail for Nancy. He says we need keys to get into most
    MWD sites. He will be back next week.

    Will Prescott and Rahul Bahadur did recon in the LA Basin. They looked at 2 Metropolitan Water District sites: sites, 3 Caltrans sites, and 1 USGS-WRD site. They also found possible sites by serendipity. See Aug 29 A Team recon for a summary of their results.

    John Galetzka turned over to Nancy the results of USGS-Pasadena's recent recon of Ventura County. They found seven possible sites, and three that we might be able to use if we have to. See August A Team Ventura County recon for a summary of their results.


    September 2, 1997
    Tuesday

    Bruce Luyendyk sent e-mail to Nancy King to say that he has done extensive recon in Santa Barbara County. Nancy passed this information on to Bob Packard.

    September 3, 1997
    Wednesday

    Frank Webb, one of the three members of the new Dots Committee (Agnew, Webb, King), will be on vacation until September 23.

    John Galetzka is pursuing two contacts:

    Will Prescott will spend next Monday doing reconnaissance.


    September 4, 1997
    Thursday

    Nancy King and Mike Duffy arranged for Mike to show
    MWD property to Will Prescott next Monday. They will look at (time permitting)

    The new Dots Committee (Agnew, Webb, King) will meeting September 23, when Frank Webb returns from vacation.


    September 5, 1997
    Friday

    Bob Packard is in touch with UC Santa Barbara, and with the Santa Barbara County Surveyor. He is also about to contact the city of Long Beach.

    September 8, 1997
    Monday

    John Galetzka met Mike Duffy of MWD to look at sites.
    Metropolitan Water District (MWD) is very interested in having SCIGN sites on their property. They want to use them as control points for their surveys. When there is a big earthquake, they want deformation maps ASAP in order to decide where they should check first for damage to their 10-12 foot underground pipes. John and Mike looked at

    All except the Venice Power Plant are excellent sites. The Venice site is uncertain; Mike Duffy will check MWD records for information about underground utilities and fill.

    Will Prescott, who was stuck in traffic and was unable to meet Mike Duffy, went to look at Caltrans sites instead. The traffic jam served us well, because we ended up looking at more sites. See Sep08 A Team recon for a summary of the day's results.

    Bob Packard will come by tomorrow to deliver the Santa Barbara County map, and to pick up more SCIGN booklets.

    Ken Mills, of PacBell, called Nancy regarding permission to use their facilities. Many TriNet sites are on PacBell property. Ken only handles universities, so he will have the "government" person call Nancy.


    September 9, 1997
    Tuesday

    Nancy gave the "A Team" (USGS-Pasadena, led by John Galetzka) 34 more sites to look at this week. Reports will appear daily.

    Nancy is also preparing a list of sites for the "B Team" (Scripps, led by Yehuda Bock). Yehuda returns to Scripps on Thursday.

    Bob Packard delivered a map from Ed Villa, Santa Barbara County Surveyor. There are potential sites from Public Works, fire stations, and county parks. Bob will contact the Department of Water and Power, continue recon along Profile A, and help with permitting within L.A.

    Mike Watkins and Nancy spoke (after playing phone tag for days) to clarify who will do what in Santa Barbara County. JPL will work with Bruce Luyendyk (UC Santa Barbara) to put in rock pin monuments on Santa Cruz Island and on Santa Ynez Peak. JPL and UCSB are working to find a place to put UCSB's third receiver. All three of UCSB's sites will be installed by JPL, not the contractor. For other sites in Santa Barbara County, either JPL or USGS will do the recon.

    The PacBell person handling land use permits for USGS called. Nancy sent a copy of the SCIGN booklet to P.J. Pandya. He will get back to Nancy early next week.

    Nancy called Mike Duffy of Metropolitan Water District (MWD) to thank him for his efforts on yesterday's reconnaissance, and to plan more recon work. This Friday, Mike and John Galetzka will look at (time permitting)

    The "B Team" (SIO) will look at the other MWD sites. Mike says there may be other sites, too. For now, we will pursue the 24 sites he gave us. We will not need a building permit for any sites on MWD property. However, we will have to get approval through MWD Operations. Mike says this will not be too difficult, since MWD has dealt with SCIGN before (Lake Matthews, Skinner), and is anxious to have our sites on their property.

    Nancy called Bill Young to get the phone number of a contact for Riverside County. Bill also said that he is sending a list of sites in Orange County and Victorville.

    Nancy called Bob Jackson, Riverside County, to notify him that the "B Team" will shortly want to look at Riv. Co. sites.


    September 10, 1997
    Wednesday

    The A Team looked at six
    Caltrans sites yesterday. Four were unsuitable, one was uncertain, and one is a "backup" site (that is, we could use it if nothing better were available in the area). See Sep09 A Team recon for a summary of the day's results.

    Nancy received from Bill Young a list of fire stations in Orange County, and two stations in Victorville.

    In the evening, Nancy King and John Galetzka attended a meeting of the California Land Surveyors Association (CLSA). The speaker was Inspector Mark A. Tolbert, of the LA County Fire Department. The topic was the hazards facing surveyors, from gangs, fires, and toxic substances. These are issues we should consider when choosing SCIGN sites.


    September 11, 1997
    Thursday

    The A Teams (Galetzka, and Aspiotes/Van Wyk) looked at ten sites yesterday, mostly
    Caltrans and mostly unsuitable. See Sep10 A Team recon for a summary of the day's results. So far, a high percentage of the Caltrans sites are not suitable, while most of the Metropolitan Water District (MWD) sites are.

    September 12, 1997
    Friday

    The A Teams (Galetzka/Bahadur, and Aspiotes/Van Wyk) looked at 11
    Caltrans, TriNet, and LA County sites yesterday. Only two were suitable. See Sep11 A Team recon for a summary of the day's results.

    Yehuda Bock and George Liu met with Nancy King at USGS-Pasadena. George, an engineer from UNAVCO, will be the B Team. The B Team reconnaissance assignment includes sites in Riverside County, San Bernadino, Orange, and San Diego counties.


    September 15, 1997
    Monday

    Last Friday, the A Team went on three separate recon expeditions. Aspiotes and Bahadur looked at three
    Caltrans site and one TriNet site; only one site was suitable, and only as a backup. Galetzka and Van Wyk, accompanied by MWD Chief Surveyor Mike Duffy, looked at four Metropolitan Water District (MWD) sites. One was suitable, and another was uncertain. Ken Hudnut looked at three dams in the San Gabriel Mountains ( LA County); two were suitable. See Sep12 A Team recon for a summary of the day's results.

    Eldon Gath, John Scheid, Ken Hudnut, and John Galetzka met at USGS-Pasadena. The start-up contract is in place, and Eldon Gath, Tanya Gonzalez, and Greg Helmer are available for consultation. John Scheid will be kept in the loop. Everyone agreed that the contractors should see the sites selected by the Dots Committee. When the main contract starts, USGS will turn over the site databases and the ArcInfo map to the contractor. There will be another meeting next week, Tuesday September 23.


    September 16, 1997
    Tuesday

    This week the A and B Teams will be looking at
    LA County and Riverside County facilities.

    Bob Packard delivered maps from the Department of Water and Power (DWP). This agency is very eager to have SCIGN sites on their property.

    On Friday, Ken Hudnut will visit Big Dalton and Cogswell Dams with Mike Long of LA County.


    September 17, 1997
    Wednesday

    The A Team looked at four
    LA County facilities. Three were unsuitable, and one was uncertain. See Sep16 A Team recon for a summary of the day's results.

    George Liu visited USGS-Pasadena. The B Team looked at 17 sites, mostly from Riverside County on September 12 and September 15. Two of the road yards were suitable, and the Sheriff's Office was clearly unsuitable. The other sites were uncertain, because of utilities. George also saw two likely facilities, a vineyard and an elementary school. See Sep16 B Team recon and Sep17 B Team recon for a summary of the 6 results.

    Nancy King spoke with Dave Pierce of the Orange County Fire Department. After inquiries initiated by Bill Young and John Canas (County Surveyor), the Fire Authority provided us with a list of 58 fire stations. The Fire Authority is interested in Differential GPS, a service that we cannot provide right now but may offer in the future. However, the Fire Authority, while willing to cooperate, does not have the same interest as MWD or DWP. Dave Pierce is going to try to "sell" SCIGN within the Fire Authority, and will also investigate permitting.


    September 18, 1997
    Thursday

    The A Team looked at 19
    LA County facilities yesterday. Four were suitable, six were uncertain or backup sites, and nine were unsuitable. See Sep17 A Team recon for a summary of the day's results.

    Today, John Galetzka (A Team), George Liu (B Team), Eldon Gath (contractor, Earth Consultants International), and Mike Duffy (MWD Chief Surveyor) are visiting Metropolitan Water District (MWD) sites.

    Nancy King checked back with facilities reconned by Bob Packard (see Profile A, Bob Packard's report, Aug. 21 meeting and Aug. 28).

    The California Water Service Company and the South Coast Botanic Garden are typical of organizations that don't want SCIGN sites for their own purposes. The approval process is very slow. They are willing to have us, but they are not going to put our request at the top of the list. In contrast, Mike Duffy of Metropolitan Water District (MWD) has made three separate recon expeditions with the A Team in the last two weeks, and will work hard with his Operations Department to find the best spot at each site.


    September 19, 1997
    Friday

    On yesterday's trip to
    Metropolitan Water District (MWD) facilities, Galetzka (A Team), Liu (B Team), Gath (contractor, Earth Consultants International), and Duffy (MWD) looked at five sites. Two were suitable. Three were uncertain, because of proximity to fault zones or existing SCIGN stations. Meanwhile, Bahadur looked at the USC Health Services Campus. He found a possible site. Another part of the A Team (Aspiotes and Van Wyk) looked at 14 LA County sites. Only one was suitable. Five were unsuitable. The rest were uncertain, in many cases due to problems with getting in. See Sep 18 A/B Team recon for a summary of the day's results.

    Nancy King used the DeLorme map program to obtain latitudes and longitudes for the Department of Water and Power (DWP) power facilities. Several are in excellent locations. Nancy left voice mail for the Chief Surveyor on the "power" side of DWP.

    Nancy left voice mail at the Public Works Department of the City of Placentia. They have offered one site, at city hall.


    September 22, 1997
    Monday

    Bill Young sent Nancy King a list of 15 possible sites in San Bernadino County, and two in Victorville.

    The A Team looked at a number of LA County sites. See Sep 19 A Team recon for a summary of the day's results.


    September 23, 1997
    Tuesday

    John Galetzka reported that, after examination of borehole logs and cut and fill maps, geology at the
    Metropolitan Water District (MWD) Foothill Feeder Facility is OK. This site, previously a "no," now becomes a "yes."

    George Liu, the B Team, has created a Web page. See http://www.unavco.ucar.edu/~liu/scign.html for information about the B Team reconnaissance results. Nancy will also summarize his results here.

    Jake Madigan of DWP called Nancy King. He will help us with both the water and power "sides" at DWP, but cannot do anything until next week. This week, Nancy will use the DWP maps obtained for us by Bob Packard to determine which DWP facilities are of most interest to us.

    The new Dots Committee (Duncan Agnew, Frank Webb, Nancy King) met for the first time at USGS-Pasadena.

    SCIGN people met with the contractor for the second time. There was discussion of many issues, but only site recon discussion is described here.


    September 24, 1997
    Wednesday

    Don D'Onofrio (NGS, California State Advisor at Caltrans) sent Nancy King a list of Caltrans contacts. A map is also coming, in the mail.

    Yesterday, the A Team looked at 11 LA County facilities. Nine were unsuitable, and two were uncertain (possible if we really need something in that area). See Sep 23 A Team recon for a summary of the day's results.


    September 25, 1997
    Thursday

    George Liu, the B Team, visited five TriNet sites yesterday. Only one was suitable. See
    Sep 24 B Team recon for a summary of the day's results.

    Nancy King called Eldon Gath (Earth Consultants International). Nancy will send Tania Gonzalez (via e-mail) information about the sites selected by the Siting Committee on Tuesday. Tania will look at geologic maps to see whether these sites look suitable. This is necessary since it is often difficult for the recon crews to determine geology while standing in a parking lot. Nancy will cc the e-mail to Eldon and to John Scheid (JPL).

    Nancy King and Chris Becker (Public Works, City of Placentia) played phone tag about a possible site in Placentia.

    Nancy King, in separate conversations with other members of the Siting Committee (Duncan Agnew and Frank Webb), discussed whether to pursue possible sites in Escondido. Bill Young approached Escondido, and they offered three possible sites. However, the general plan does not include sites in San Diego County, and the Siting Committee plans to preserve the station density of this plan. The committee agreed that, since the sites were offered, it is worth it to send a recon crew to Escondido. We don't want to slam a door that we may someday want open.

    Nancy King left voice mail for Pat Thomas, Assistant Director of Public Works for Escondido.


    September 26, 1997
    Friday

    Bob Packard called Nancy King. He has approached Compton and Dominguez Hills Colleges, and has received an enthusiastic response. Someone from USGS will accompany him to Compton College next week, since Bob feels that that may help clinch the deal.

    Nancy King and Chris Becker (Public Works, City of Placentia), finally connected. He responded to Bill Young by offering a site at city hall. It turns out that this site is on top of a building. After he understood our needs better, he offered a city corporation yard. It has security, utilities, and sky view, and no one cares if it's pretty. Someone from USGS will meet Chris next Thursday to look at this site.

    Nancy King and John Buntrock (Caltrans District 12, Orange County) played phone tag. We have not yet looked at any District 12 sites, and need a list.

    Nancy sent information about new sites to Tania Gonzalez, as described yesterday.


    September 29, 1997
    Monday

    Nancy King is behind posting the recon results, because she's been clambering farther up the GIS learning curve. Results will be posted in the next few days.

    Nancy and Pat Thomas finally connected, and discussed a possible site in Escondido. Although Pat had thought of three possible sites, during the conversation it became clear that the city corporation yard was probably the best bet. Nancy e-mailed Pat's name and number to George Liu (the B Team). Pat will look at the corporation yard with George.

    Nancy sent George Liu a list of sites to recon. These are in Escondido, Riverside County, San Bernadino County, and Victorville. Some of these sites are far from LA, and we probably wouldn't do them first. However, in the absence of other sites, George might as well look at them. We'll want to build sites in these areas eventually.

    Nancy spoke to Jake Madigan, of the Department of Water and Power (City of LA). Nancy looked at DWP maps provided by Bob Packard, and faxed to Jake the names of those we'd like to look at. DWP is going to do the initial recon; SCIGN people will look at DWP sites after this first cut.

    Nancy received a map of Caltrans maintenance yards from Don D'Onofrio. Nancy continues to play phone tag with Caltrans District 12 (Orange Co.)

    John Galetzka went to Bracket Field, one of the new sites, to start the permitting process.

    Last Friday, Ken Hudnut and Aris Aspiotes visited Cogswell, San Gabriel, and Morris Dams. They were accompanied by LA County people. All three of these dams look like good possibilities. The LA County people also told Ken and Aris that the county has right-of-way along the San Gabriel River (roughly, along the 605 freeway). This right-of-way might offer some possible sites.


    September 30, 1997
    Tuesday

    Bob Packard called Nancy King to report that he is visiting Compton and Dominguez Hills Colleges on October 7. John Galetzka will accompany Bob to Compton College, since Bob feels that the presence of a SCIGN person will make the approval process quicker.

    Nancy spoke to Dick Stewart, Caltrans District 7. For approval on our proposed new site at the Caltrans Bellflower facility, he referred us to John Adams (Survey Office Supervisor).

    Nancy spoke to John Buntrock, Caltrans District 12 (Orange County). He will fax a list of District 12 facilities.

    Nancy left a message for our contact at the Orange County Fire Department. We are awaiting approval to visit the fire stations.


    October 1, 1997
    Wednesday

    Nancy King and John Galetzka visited four possible sites found earlier by Bob Packard. See
    Oct 01 A Team recon for a summary.

    October 2, 1997
    Thursday

    Nancy King received a list of stations from Caltrans District 12 (Orange County).

    George Liu called Nancy King to report that he had found a small water district in Hemet that looked promising. Someone from that organization will show him around tomorrow. George also reported that he found a possible site in Escondido. Nancy will post those results soon, when logs and coordinates arrive.

    The A Team visited a corporation yard in Placentia, an MWD facility, and LA County dams. See Oct 02 A Team recon for a summary.


    October 3, 1997
    Friday

    Nancy King finally brought the posted recon results up to date. See
    Recon Notes to see an updated list of links.

    Bill Young called Nancy King and Ken Hudnut to report that he has contacted Kern County.


    October 5, 1997
    Sunday

    Nancy King presented the recon results to the SCIGN Board.

    October 6, 1997
    Monday

    SCEC meeting.

    Dan Ponti told Nancy King about a Hollywood site. This site has, or will have, several types of instruments, and SCIGN may be able to use it too. Dan will e-mail a site description to Nancy.


    October 7, 1997
    Tuesday

    SCEC meeting.

    Bob Packard, John Galetzka, and Shannon Van Wyk visited Compton and Dominguez Hills Colleges. Both sites were suitable. See Oct 07 A Team recon.


    October 8, 1997
    Wednesday

    John Galetzka met with LA County about permitting of the new sites. John now has many contacts with various county organizations.

    George Liu delivered a new set of B Team results.


    October 9, 1997
    Thursday

    Almost all SCIGN people from southern California attended the demonstration installation of the new site at Lake Skinner.

    October 14, 1997
    Tuesday

    Because of the SCEC meeting and the Lake Skinner installation, last week was mostly a lost week for Nancy King. During last week, however, John Galetzka carried on permitting for the
    new sites, and George Liu continued recon in Riverside and San Bernadino Counties.

    Nancy got caught up with recon logs, mostly from George (the B Team), today. See the new links at the bottom of the Recon Notes page. Since George has changed some of his initial "uncertain" results, Nancy also updated older results as required.

    Lloyd Gibson, Caltrans District 6 (used to be 5), called Nancy to ask what he could do for SCIGN. He was present at Don D'Onofrio's talk to Caltrans last month; it must have been a good talk because Lloyd called me before Nancy called him. District 6 is in San Luis Obispo. Nancy sent Lloyd a SCIGN brochure, and Lloyd will send us a list of District 6 facilities.

    Nancy, John Galetzka, Bob Packard, and Bill Young will meet this Thursday at 1 pm. Bob Reader is on vacation.


    October 15, 1997
    Wednesday

    There was a conference call among the following people:

    Many issues were discussed, but only site reconnaissance is described here. We decided to have SCIGN people continue the recon effort, at least for now. We did not decide exactly when the contractors will take over this work. For now, Bill Young, Bob Packard, and Bob Reader will continue to find potential sites for us, and we will continue to evaluate them. This work goes fairly quickly, so permitting is the highest priority. John Galetzka is handling that for the A Team; Paul Jamason will do it for the B Team. JPL is beginning recon in Ventura County, and will install two sites for Bruce Luyendyk in November. Right now, since we don't have all the equipment yet, site recon is not getting in the way of the site upgrades. When everything is ready, JPL and Scripps will work on the upgrades. This is especially convenient because JPL has to install met packages (for El Nino) anyway.

    After the conference call, Paul Jamason met with John Galetzka to become familiar with the permitting process.


    October 16, 1997
    Thursday

    James Stowell and Dave Rutledge of Ashtech met with Ken Hudnut, John Galetzka, and Jeff Behr at USGS-Pasadena. Among the many topics discussed was real-time kinematic GPS. A receiver-independent format is now available, so that it is possible to do RTK without worrying about the receiver brand. This is important for site recon, because some of the agencies we are dealing with do RTK and do not have Ashtech receivers. This new receiver-independent capability is available with the firmware we are using, and will make the SCIGN project even more attractive to these agencies.

    Nancy King called Jake Madigan, Chief Surveyor at DWP (Department of Water and Power). He has looked at both water and power installations, and has picked out potential sites for us. He and John Galetzka will tour these sites next week. DWP is one of the agencies using RTK.

    Nancy King, John Galetzka, and Ken Hudnut met with two of our three surveyor volunteers. Nancy reported that nothing is happening with the Orange County Fire Department; they are not hostile to our project, but it is not very important to them. Bill Young has contacts with interested cities in Orange County, and has already talked to some of them. He will pursue this, and in Orange County we will look at city and Caltrans District 12 facilities. Bill will also get back to the Kern County surveyor, and find a few more sites in eastern San Bernadino County. For eastern Riverside County, he suggests talking to the Metropolitan Water District. Bob Packard will continue reconnaissance along Profile A.


    October 17, 1997
    Friday

    The A Team went out yesterday to take a second look at a few sites. They made the following decisions:

    October 20, 1997
    Monday

    Last Friday, the A Team looked at five
    Caltrans sites in District 12 (Orange County). All were unsuitable. See Oct 17 A Team recon for a summary of their results.

    Nancy King received copies of recon logs from the B Team, and used these to add more information to Oct 09 B Team recon and Oct 10 B Team recon. The earlier versions of these were from George Liu's B Team Web page.

    There was a meeting at JPL, attended by:

    Many issues were discussed. Regarding site reconnaissance, it was agreed that SCIGN will find 75 sites and take 25 of these all the way through the permitting processing.

    October 21, 1997
    Tuesday

    Nancy King began using the sites found suitable by recon crews (although not necessarily chosen as new sites) to compile statistics on how many sites need (1) solar panels and radio modems, (2) repair to paved areas or landscaping after trenching, or (3) fences. This information is needed for contract discussions, since these items increase the costs.

    October 22, 1997
    Wednesday

    John Galetzka toured Department of Water and Power (City of Los Angeles) sites with Jake Madigan of DWP. They looked at four power facilities selected earlier by Madigan. All were suitable.

    October 23, 1997
    Thursday

    John Galetzka toured Department of Water and Power (City of Los Angeles) sites with Jake Madigan of DWP. They looked at four water facilities selected earlier by Madigan. All were suitable. They also saw a DWP communications facility, also suitable. Jake Madigan is going to start the DWP permit process for all these sites, although he understands that the SCIGN Siting Committee may not accept all of them. DWP is now in turmoil, because they are in the midst of downsizing and reorganization (where have I seen that before?). However, Madigan really wants SCIGN sites, and will do his best to push these permits through. It is also possible that DWP will let us install repeaters at their communication centers, or even share their microwave comm systems.

    Shannon Van Wyk, USC employee now working at USGS-Pasadena, has been searching for GIS coverages that will be useful in our recon. Shannon worked as a GIS technician for the state of Iowa. She has connected with a GIS person at the Metropolitan Water District. MWD has already assembled coverages of active water wells. This should be very useful.

    Nancy King sent the particulars of 47 potential new sites to the other two members of the Siting Committee (Duncan Agnew and Frank Webb).


    October 24, 1997
    Friday

    Nancy King, in preparation for another meeting at JPL next Monday, assembled statistics from the site reconnaissance done so far. Here are the results (the short version)


    October 27, 1997
    Monday

    Nancy King reported the results above at a meeting at JPL. The same people who were present on
    October 20 were at this meeting, minus Yehuda Bock.

    John Galetzka reports that the permitting process on the new sites continues to simmer. We are finding that permitting, even with agencies which want SCIGN sites for their own purposes, is a very lengthy process. We underestimated how long this would take when we began this work.

    Nancy King received a package of site reconnaissance logs from George Liu. Results will posted as soon as Nancy can find the time to do it.


    October 28, 1997
    Tuesday

    Shannon Van Wyk of USGS-Pasadena visited a GIS expert at the
    Metropolitan Water District. They have many GIS coverages, such as water wells, that we can incorporate in our reconnaissance work. Shannon, a new employee at USGS, has several years of experience as a GIS technician for the Iowa Department of Natural Resources.

    October 29, 1997
    Wednesday

    Orange County:

    Thanks to Bob Packard, the LA Harbor Department is interested in getting a site and tying it to the famous Tidal 8 benchmark.


    October 30, 1997
    Thursday

    Yesterday's Los Angeles Times had a front-page article on the downsizing at the Department of Water and Power. They are planning to lay off 2000 people. In spite of this turmoil, DWP's Chief Surveyor Jake Madigan is so interested in having SCIGN sites that he is actively pursuing the permitting of the sites looked at on
    October 23. In a phone call to John Galetzka, he reported that he has already talked to local operations staff about several of the proposed sites. They object to some of the locations, and want them moved to, say, the other side of the facility. These changes may require re-evaluation by Galetzka.

    John Galetzka and Paul Jamason will meet with Riverside County the week of November 10. An earlier meeting for this week was re-scheduled at their request. The purpose of the meeting is the permitting of sites in Riverside County.

    John Galetzka has set up a meeting with Los Angeles Southwest College, in Hawthorne. They are quite interested.


    October 31, 1997
    Friday

    Will Prescott and Rahul Bahadur are doing separate recon of some
    LA County sites today.

    John Galetzka will be at Ashtech next Tuesday. He will do some recon in San Luis Obispo County on the way north, and will look at the Lake Isabella TriNet site on the way home. The latter site is on top of a dot.

    Nancy King got caught up and posted results for


    First week of November, 1997

    Nancy King is working less on site reconnaissance for the month of November, in order to revise a JGR paper and prepare a long-promised seminar. Here's what has happened since the last update:

    November 13, 1997
    Thursday

    The Siting Committee (Duncan Agnew, Frank Webb, Nancy King) met, and accepted 28 new sites. Of the 17 sites accepted on
    September 23, 2 have proved to be unsuitable on further inspection and 2 have been replaced by 2 of the 28 new sites. Thus the total number of accepted sites is now 41. See Siting Committee Decisions.

    John Galetzka and Bob Packard visited Downey and Paramount High Schools. The schools, along Profile A, are anxious to have SCIGN sites.


    January 13, 1998
    Tuesday

    We're back! This log was interrupted because Nancy worked on a manuscript revision for all of November, and then took a long vacation in December. During that time, John Galetzka (USGS), Shannon Van Wyk (USGS), and Paul Jamason (SIO) have taken over the work and have done a great job.

    Nancy will resume regular updates of this log. To see what John and Shannon have been up to, check out John Galetzka's site recon page.


    January 15, 1998
    Thursday

    Bill Young called Nancy King to report that he will meeting with the Kern County Surveyor on January 22. They are very interested in having SCIGN sites at county maintenance yards.

    January 19, 1998
    Monday

    John Galetzka handed over to John Scheid information for the following 22 stations:
    Land-use agreements are imminent for these sites. John Scheid will pass on the information to Eldon Gath.

    January 22, 1998
    Thursday

    The Siting Committee (Duncan Agnew, Frank Webb, Nancy King) will meet Tuesday, Jan. 27.

    The USGS-Pasadena field crew has been visiting schools this week. In general, schools are anxious to have SCIGN and give verbal approval fairly rapidly. However, it's hard to say how long formal Land Use Agreements will take.


    January 23, 1998
    Friday

    Bob Packard and Shannon Van Wyk are working together to create a comprehensive list of school sites to present to the LA Unified School District.

    Nancy King and maybe Ken Hudnut will attend the National Height Modernization Forum in Ontario, CA, next Monday. NGS people and surveyors will attend, and are very interested in SCIGN. Yehuda Bock will attend a satellite meeting of surveyors to discuss using SCIGN to define a reference system.

    Bill Young has met with surveyors from various cities and counties, and has or will soon get lists of possible sites from

    Bill Young also reports that Texaco plans to build a continuous GPS site at their facility about 30-40 miles east of Bakersfield. This site will be in an oil field. However, we're not paying for the site, and the data will be there if we want it. Furthermore, Texaco has an underground pipeline network across southern California, and we might be able to use their property along that network. These sites would not be in oil fields.

    January 27, 1998
    Tuesday

    The Siting Committee (Agnew, Webb, King) met to consider the many potential sites scouted out in the past two months by John Galetzka, Shannon Van Wyk, Rahul Bahadur, Nami Kitchen, and Paul Jamason. The committee accepted most of them, and also agreed to recent substitutions and rejections. The total number of accepted sites is now 90. See
    Siting Committee Results for a list of accepted, backup, and rejected sites.

    The Siting Committee also decided to revisit the question of whether we need a person doing nothing but permitting. Since we now have 90 accepted sites, Nancy King and John Galetzka will review permitting status in detail. John Galetzka, Shannon Van Wyk, and Paul Jamason have been handling permitting so far, but they have also been doing other things. Much of the permitting is out of our control (for example, some agency's real estate people have to look at it), but we may be able to speed it up. It may be time to take someone out of the truck and onto the phone all day.

    Experience at Rialto High School shows that the auger rig needs room to maneuver around the site (a radius of about 50 feet, according to Frank Wyatt). Knowledgable people (Galetzka, Hudnut, Webb, Wyatt, Agnew) will re-examine photos and site sketches of accepted sites to make sure we won't have trouble.


    January 29, 1998
    Thursday

    John Galetzka and Shannon Van Wyk obtained land use agreements (LUAs) for nine sites.
    Siting Committee Results now has a column indicating which sites have LUAs. When we get an LUA for a site, it is ready to go to the contractor.

    January 30, 1998
    Friday

    Bob Packard, John Galetzka, Shannon Van Wyk, and Nancy King met to discuss the status of sites at schools. Packard and Van Wyk have worked on this almost exclusively, and will continue to do so. LA Unified School District (LAUSD) wants us to pick a specific site at each school, obtain local approval, and then submit a "package" of many schools to LAUSD. Bob Packard will call our contact at LAUSD to figure out how to expedite the permitting process once we submit the package. We hope that, if we offer to "walk it through," we can speed up the permitting process significantly.

    The permit from the Metropolitan Water District is almost ready.

    On the list of accepted sites ( Siting Committee Results ), La Puente High School replaces California Elementary School. They are very close to each other.


    February 02, 1998
    Monday

    John Galetzka is on a two-day trip to pick exact monument locations at Department of Water Resources (DWR) sites in Kern County (Alamo, Buena Vista, and Edmonston Pumping Plants).

    Shannon Van Wyk, Nami Kitchen, and Bob Packard will visit various Los Angeles public schools this week.


    February 04, 1998
    Wednesday

    Bill Young sent Nancy King a list of 17 possible sites from the Kern County Surveyor.

    February 05, 1998
    Thursday

    Thanks to the efforts of Paul Jamason, the land use agreement Beaumont Road Yard (Riverside County) will shortly be signed.

    Bill Young sent Nancy King the positions of three possible sites in Orange County.


    February 09-12, 1998
    Monday-Thursday

    USGS-Pasadena Web pages were being put on a new server this week, so this update will cover the last four days.

    On Monday, Bill Young, Nancy King, John Galetzka, Paul Jamason, and Myra Medina attended an expanded meeting of the SCIGN Executive Committee.

    Shannon Van Wyk and Bob Packard continue to work on preparing a "package" of sites to go to the LA Unified School District.

    Two accepted sites will probably have to be dropped. At Roosevelt High School, the principal rejected all possible sites found by John Galetzka. The Rosemead school board is worried about liability, so Rosemead High School is probably out.

    The MWD permits are now in the hands of their bureaucracy, awaiting the last few signatures. Perris Power Plant did not get into this first package of sites. It will go in the second package, being prepared now. We, and our MWD contact, are now much more savvy about what it takes to get permits through. On Wednesday, John Galetzka and Mike Duffy of MWD looked at possible sites east of the Salton Sea. These sites are along MWD's pipeline from the Colorado River.


    February 16-20, 1998
    Monday-Friday

    This page will not be updated this week, since Nancy King is in Menlo Park. John Galetzka, Shannon Van Wyk, Bob Packard, and Paul Jamason continue working on permitting.

    February 23-26, 1998
    Monday-Thursday

    Several sites previously accepted by the Siting Committee (Agnew, King, Webb) have fallen off the sled. These are: Several sites have problems, but it still might work out: Several sites have changed name: Several new sites have been accepted by the Siting Committee:

    The list of accepted sites has been changed to reflect these changes.

    About the long-awaiting MWD permit: The bad news is that, although it's been "imminent" for weeks, we still don't have it. Mike Duffy says probably next week, after they pry it out of the hands of their lawyers. The good news is that this delay allows us to sneak the four recently-approved MWD sites (above) onto the same permit.

    "Packages" of sites will be submitted (by John Galetzka and Shannon Van Wyk) to the LA Unified School District and the Department of Water Resources.

    Thanks to Bill Young, the Kern County, Santa Barbara County, City of Santa Ana, and City of Costa Mesa surveyors are eagerly awaiting recon by SCIGN. They are aware that we will get to them as soon as we've finished the current batch of stations. We define "finished" as in the hands of the agency, with no more work required of us except for periodic checks on status.


    March 02, 1998
    Monday

    John Galetzka handed over to Bob Packard a packet of permitting information for the Los Angeles Unified School District. Bob will make an appointment to hand the packet to district officials, and find out what we can do to expedite permitting.

    John Galetzka and Mike Duffy of MWD decided to use the Hinds Pumping Plant (see the "Several new sites ..." list in the previous entry). Hinds, Iron Mtn, and Gene Pumping Plants will definitely make it onto the MWD permit. This permit should be issued in a few days. Yes, we've said this before, but this time we really mean it.


    March 03, 1998
    Tuesday

    Oak Flat Ranger Station, previously accepted by the Siting Committee, is now out. Although on land controlled by the Forest Service, the site is actually leased to USFS by Chevron. In John Galetzka's judgment, this ownership situation would be very difficult to permit. Since it is fairly easy to find sites but hard to permit them, we say "forget it." The list of
    accepted sites has been changed to reflect this change.

    March 12, 1998
    Thursday

    The Siting Committee met March 5 to consider several more sites. One, Quartz Hill, is still under discussion. However, since it's been a week since the meeting, we post the results here even though they are not final. See
    the list of accepted sites.

    Bill Young is meeting with the City of San Clemente today. Bill also reports that Art Veron, former Ventura County surveyor, has volunteered to look for sites in that county.

    John Galetzka and Paul Jamason are on a road trip, visiting and in some cases re-visiting sites in Orange, Riverside, and San Diego Counties.


    March 17, 1998
    Tuesday

    El Camino Real High School, previously on
    the list of accepted sites, has not worked out. They rejected every possible spot selected by the recon crews, and a nearby alternative (Hale Elementary School) didn't work out either.

    March 18-27, 1998

    Permit update (mostly repetition of the material presented at the SCIGN meeting on March 24):
    The Venice Power Plant (an MWD site) has fallen off the sled due to too many underground utilities. John Galetzka checked out a nearby alternate site proposed by MWD, but it was not suitable.

    Mark Smith (JPL) is joining the recon effort.


    March 31, 1998
    Tuesday

    A meeting about reconnaissance in Ventura and Santa Barbara County took place at USGS-Pasadena:

    April 01, 1998
    Wednesday

    John Galetzka (USGS) and Paul Jamason (SIO) visited three sites in Orange County. These are the cities of Costa Mesa and Santa Ana (thanks to Bill Young for preparing the way here), and Cypress College. All three prospective sites look good. John spoke to all of them about expediting permitting, and they said this could be done. Of course, as we have found before, there can be delays at higher levels even when surveyors or teachers are very enthusiastic.

    April 06, 1998
    Monday

    Bell Gardens Intermediate School has concerns about liability, but we think we can solve them quickly. The school district attorney wanted a certificate of insurance, which USGS cannot provide since the federal government simply pays for damage ("self-insures") under the Federal Tort Claims Act. We also told the school that we can build a fence. A land-use-agreement should follow quickly once this question is resolved.

    Bob Packard called Nancy King to report on progress at the Los Angeles Unified School District. They seem to be on top of the land use agreement procedure. The LAUSD sent our proposal for the various sites out for comments, which are due back this Thursday. So, they have a timetable which seems to be fairly quick. They estimated three weeks for the permit process.

    Last Friday, John Galetzka and Shannon Van Wyk worked on wrapping up USGS sites-in-progress in Ventura County. The rest of this work will be handled by Mark Smith of JPL.


    April 07, 1998
    Tuesday

    Paul Jamason of SIO reports that:

    April 08, 1998
    Wednesday

    Yesterday, John Galetzka and Shannon Van Wyk visited Malibu and Fairfax High Schools, both in the LA area. Both are suitable, although security at Fairfax needs to be investigated further.

    April 09, 1998
    Thursday

    Santa Monica Airport looks like a good replacement for Venice Power Plant, a previously accepted site which ultimately had to be rejected due to underground structures. Shannon Van Wyk is pursuing inquiries.

    Yesterday, John Galetzka and Paul Jamason visited sites in Orange and San Diego counties. They met with the surveyors from the City of San Clemente, who are very enthusiastic about SCIGN. No specific site has been selected yet, but John and Paul are confident that one can be found.

    The Siting Committee (Agnew, Webb, King) met today. The committee is getting pickier now, and re-thinking a few previous decisions. This is because now, with approximately half the new sites chosen, the committee is painfully conscious that there can only be 200 new sites. The committee is now associating every accepted site with a dot, and removing that dot from the map. See list of accepted, backup, and rejected sites.


    April 14, 1998
    Tuesday

    John Galetzka reports that we now have permits for Southern California International Airport and Frazier Mountain High School, for a total of 16 signed land use agreements. See
    list of accepted, backup, and rejected sites.

    This log will be sketchy this week, since Nancy King has relatives in town and will not be in the office much.


    April 20, 1998
    Monday

    Last week, land use agreements were obtained for La Puente High School, Valley Alternative School, and Burke Middle School. We now have 19 LUA's.

    Also last week, John Galetzka and Shannon Van Wyk visited Santa Barbara County, and met with the county surveyor. They found several possible sites.

    Mark Smith continues to find possible sites in Ventura County.


    April 22, 1998
    Wednesday

    We have land use agreements for two campuses of Long Beach Community College. One will be a new site, and the other can eventually replace the building site now at existing site LBCH.

    April 28, 1998
    Tuesday

    We now have land use agreements for Santa Felicia Dam, South Pointe Middle School, and Mesa Union School. The total number of LUA's is now 23.

    To see up-to-date maps of existing and accepted sites, at three scales, click on All sites, Greater LA area, or Closeup of LA Basin. These links are also at the top of list of accepted, backup, and rejected sites. Shannon Van Wyk also created maps with station labels; links to these live on the SCIGN home page. Look under "Overview of SCIGN" in the upper right corner, then under "Station Location Maps."


    May 01, 1998
    Friday

    Recently John Galetzka and Paul Jamason evaluated sites in San Diego County. San Vicente Reservoir is not suitable for drilling, so this site has fallen off the sled. Brown Field looks OK. John and Paul re-evaluated the City of Escondido's Water Treatment Plant and think we can do better. We will have a site somewhere in Escondido.

    Below is e-mail sent by John Galetzka to everyone involved in site recon:

    Mark Smith has found 13 sites in Ventura County, one of which (Happy Valley School, called "Highway 150 School" in previous entries) has already been accepted by the Siting Committee. The others will be considered at the committee's next meeting.

    John Galetzka and Shannon Van Wyk are considering replacing Road Division 446 with a school very close to the Road Division. They want to do this because they can get more open space, and hence better sky view, at the school.


    May 04, 1998
    Monday

    We now have a land-use agreements for Palomar Observatory and Bell Gardens Intermediate School.

    May 06, 1998
    Wednesday

    John Galetzka reports that

    May 08, 1998
    Friday

    We now have land-use agreements for the San Bernadino County stations. The number of LUAs is now 28.

    May 11, 1998
    Monday

    Oops! The entry for last Friday is premature. San Bernadino County site LUAs are still in the pipeline.

    May 13, 1998
    Wednesday

    The Siting Committee (Agnew, Webb, King) will meet tomorrow.

    MWD LUA's for the nine sites to be held by USC have arrived. This brings the total number of LUA's to 38. This number includes Compton College and Cal State Dominguez Hills.

    A recent update from Paul Jamason:

    Mark Smith has found several possible sites in Ventura County. These will be considered at tomorrow's Siting Committee meeting.

    On second consideration of sky view and space at Hollenbeck High School and Road Division 446, John Galetzka and Shannon Van Wyk have found replacement stations at California High School and East LA Science and Math Center. Also, Gabrieleno HS replaces Rosemead HS, where permitting proved impossible.

    John Galetzka is visiting Edwards Air Force Base to inspect two possible sites they have found for us.


    May 15, 1998
    Friday

    The Siting Committee met yesterday. See
    list of accepted, rejected, and backup sites

    The following sites were accepted:

    The following site was rejected: The following sites were put in the backup category:

    June 16, 1998
    Tuesday

    Over the past month, we have been discussing the site selection procedure and modifying it somewhat. This is not surprising, since we just begun interacting with the contractor. On June 2 Nancy King, Duncan Agnew, Frank Webb, Ken Hudnut, and John Galetzka met at USGS. The short version of the results is that (1) time-varying sky view and multipath may be a problem, although it is also unavoidable in certain areas, (2) the recon crews will, in the future, make quantitative sky view diagrams, (3) the Siting Committee will consider site characteristics as well as locations, (4) the EC will be the final arbiter.

    We now have 123 accepted sites, 45 land use agreements, and 4 sites built (Compton College, Cal State Dominguez Hills, Paramount High School, and Downey High School). See the list of accepted, rejected, and backup sites

    The following changes have occurred, and are now listed in the list of accepted, rejected, and backup sites:

    John Galetzka and Paul Jamason made these changes based on space, permitting, logistics, drilling, and sky view.

    Shannon Van Wyk will be working on battery upgrades this summer. The recon and permitting field crews will be John Galetzka, Paul Jamason, Mark Smith, and Bob Packard.

    John Galetzka leaves for vacation tomorrow. He'll be gone for 2 weeks. Oh no!


    June 19, 1998
    Friday

    LUA's for the San Bernadino County Sites (Apply Valley, Barstow, and Big Bear Lake Road Yards) arrived yesterday at USGS and were FedEx'd to JPL today. We also have an LUA for Baldy Mesa Road Yard, which is now a backup site.

    DWP sent copies of LUA's for Lower Franklin Reservoir and Van Norman Complex. Nancy signed them and mailed them back, so we should have fully executed LUA's for these sites soon.


    June 24, 1998
    Wednesday

    Siting Committee Meeting

    Present:

    Duncan Agnew, SIO
    Nancy King, USGS
    Frank Webb, JPL

    At recent meetings, we decided that the Siting Committee would consider the characteristics as well as locations of the proposed sites, and would give final approval to sites after ECI prepares its report. These expanded duties mean that John Galetzka should attend Siting Committee meetings, since he has the answers to many questions that arise. However, he did not attend this meeting because he is on vacation. Since we had several urgent items, we had the meeting anyway.

    (1) ECI Reports (For each site, the result appears in parentheses on the same line. Details appear in the indented paragraph.)

    (2) Questions About Sites Already Approved

    (3) Proposed New Sites

    (4) Other Business


    June 30, 1998
    Tuesday

    Paul Jamason received a draft copy of an LUA from the City of Santa Ana, for the Santa Ana Corporation Yard. We have to resolve some insurance issues.

    We received the signed LUA for West Covina High School.


    July 01, 1998
    Wednesday

    Paul Jamason reports that the LUA for Granite Reserve is gone through UC approval and now needs only minor changes of wording.

    July 13, 1998
    Monday

    John Galetzka has returned from vacation. Yay!

    John reports that the LA Unified School District (LAUSD) LUA's are almost done. LAUSD wants a report on the SCIGN education module, which John will shortly deliver to them.

    John talked to our new contact at the Department of Water Resources (DWR). This new person is very cooperative and helpful.

    John reports that it will take Los Angeles Air Force Base another two or three months to remove the large antenna near our proposed site.

    John met with Nancy to discuss the questions raised at the Jun. 24 Siting Committee meeting. They also discussed progress on the action items decided on at the June 2 meeting. The report on that meeting is not in this log, but was distributed by e-mail to the participants (Agnew, Galetzka, Hudnut, King, Webb) and to the Executive Committee.

    Sites with "action items" decided on at the June 2 meeting:

    Questions about ECI reports, raised at the June 24 Siting Committee meeting.

    Questions about approved sites, raised at the June 24 Siting Committee meeting after the committee members (plus Ken Hudnut) looked at the on-line photos. The sites below are those for which we made no decision at the meeting.


    July 16, 1998
    Thursday

    The Siting Committee met to discuss ECI reports and the information provided by John Galetzka on
    July 13.

    Present:

    Duncan Agnew, SIO
    Nancy King, USGS
    Frank Webb, JPL

    John Galetzka was not present because he was at the installation of the Frazier Mountain High School site.

    ECI Site Evaluation Reports

    Live Oak Reservoir (REJECT unless trees are cut)

    New ECI Reports

    Sites Discussed by Nancy and John Galetzka on July 13
    (This section does not include sites discussed in other sections of this report, sites for which there is nothing new to report, and sites for which we accepted John Galetzka's July 13 explanation.)

    Action Items


    August 03, 1998
    Monday

    Update from John Galetzka:

    Rio Hondo College, rejected earlier due to landslides, is back on the sled. Eldon Gath, a landslide expert, tells us that the landslide will not impact the chosen site.

    Live Oak Reservoir, rejected earlier due to poor sky view, is also back on the sled. John Galetzka and Mike Duffy (MWD) went there and selected a new site with excellent sky view. ECI will do a new site evaluation.

    Carbon Creek Control Structure turns out to be on the property of the City of Placentia, not MWD. Nancy has contacted Placentia's Public Works Department. We will be able to obtain a new land use agreement from the city.

    We're working with Mike Duffy of MWD to try to figure out whether Garvey Reservoir will be usable. At the moment, subsidence there makes this site look unattractive.

    Bill Young will work with Paul Jamason and people from Escondido to see if it's possible to find a rock site in that city.

    LA County has issued LUA's for Devil's Punchbowl Park and Eaton Canyon Nature Center.


    August 12, 1998
    Wednesday

    Siting Committee Meeting

    Present:

    Duncan Agnew, SIO
    John Galetzka, SCIGN Network Coordinator
    Nancy King, USGS
    Frank Webb, JPL

    (1) Garvey Reservoir (REJECT)

    (2) Station Density Near Tejon and San Gorgonio Passes

    (3) Reconciliation of Dot Assignment Problems

    (4) Replacement Sites

    (5) New Sites

    (6) Old Problems

    (7) John Galetzka's Report


    August 21, 1998
    Friday

    The land use agreement for Beaumont Road Yard (Riverside County) is in the mail. The other Riverside County site (Anza RY) will take a bit more time.

    Myra Medina (SIO) reports that the MWD permits to be held by Scripps are almost ready.

    Paul Jamason (SIO) reports that Escondido High School District approved the Orange Glen High School site at their recent board meeting. That LUA should be in hand shortly.

    This week John Galetzka was on a road trip with Art Varon, our latest volunteer. They have been looking at sites in Ventura, Santa Barbara, and Kern Counties. John will finish his whirlwind tour with visits to high schools in the LA Basin.


    August 26, 1998
    Wednesday

    ECI Site Evaluation Reports indicate signicant subsidence at Lake Los Angeles School and Challenger Middle School. ECI suggests nearby Lovejoy Buttes as a replacment for Challenger. They will also look around for alternatives to Lake Los Angeles School. ECI will advise SCIGN on whether it is possible to find non-subsiding sites in this region. If it is not, the Siting Committee will consider how many sites, if any, to install in this area.

    November 03, 1998
    Tuesday

    Two Siting Committee meeting conference calls were held last week, one on October 28 and one on October 30. The report below gives results for both.

    Siting Committee Meeting

    Present

    Duncan Agnew, SIO
    John Galetzka, SCIGN Network Coordinator
    Nancy King, USGS, Siting Committee Chairman
    Frank Webb, JPL

    (1) ECI's Site Evaluation Report Database

    (2) Proposed New Sites

    (3) Problems with Previously Accepted Sites

    (3) Plans


    November 12, 1998
    Thursday

    FLHS,34.40,-118.92,Fillmore High School,?

    has been replaced by

    FMTP,34.4097,-118.8937,Fillmore Teleport site

    because FLHS permitting wasn't working out. The FMTP LUA is now in hand after one week, a SCIGN record. FMPT is on a ridge east of Fillmore; the property has an antenna farm, but the proposed site is well above the antennas.


    November 13, 1998
    Friday

    John Galetzka reports that the DWR Right-of-Way Division tells him that will be working on our permits in mid-December.

    John further reports that LAUSD will send us LUAs for our signature next week. We will send them back for LAUSD signature, and then we'll be all set.


    November 18, 1998
    Wednesday

    The U. S. Forest Service reports that the LUA for Burnt Peak is in the mail.

    November 23, 1998
    Monday

    The LUA for the Elysian Park site has been stalled because a citizen thinks the monument is ugly and doesn't belong in the park. On December 2 Bob Packard, John Galetzka, and Nancy King are going to Elysian Park to meet with park people, the citizens' committee, and (we hope) some city engineers. We will try to persuade people that everyone benefits by the presence of the monument.

    The site at Seal Beach Naval Weapons Center is probably unsuitable because of geology and the presence of an Indian midden. There are probably nearby alternative sites.

    Since October, we have received LUAs for San Gorgonio Pass (SGPS), Fillmore Teleport (FMTP), Lava Bed Mountains (LBMT), Orange Glen High School (OGHS), Bell Gardens Intermediate School (BGIS), Occidental College (OXYC), Lockwood Valley Maintenance Station (LVMS), 7 LA Unified School District sites, Blink 2 (BLN2), Burnt Peak Communication Site (BRPK), and West Ord Mtn Communication Site (WOMT).


    December 23, 1998
    Wednesday

    Siting Committee Meeting December 22, 1998

    Note: The table of accepted, rejected, and backup sites has NOT yet been revised to reflect the results of this meeting. This is because Nancy discovered that she clobbered the file at some unknown time, probably before AGU. It has been reconstructed, but the version you now see on the Web is out-of-date and may contain errors. It will be checked and updated after the holidays.

    Present:

    Duncan Agnew, SIO
    John Galetzka, SCIGN Network Coordinator
    Nancy King, USGS
    Frank Webb, JPL

    Proposed New Sites

    Problems

    A Final Happy Note


    January 28, 1999
    Thursday

    Siting Committee Meeting January 28, 1999

    Present:

    Duncan Agnew, SIO
    John Galetzka, SCIGN Network Coordinator
    Nancy King, USGS
    Frank Webb, JPL

    Proposed New Sites

    Dot Reassignment

    ECI Reports

    Final Approval on Previously Accepted Sites

    Ken Hudnut's E-mail of January 27

    John Galetzka's Report


    February 08, 1999
    Monday

    Recent developments:


    March 04, 1999
    Thursday

    Recent developments:


    March 10, 1999
    Wednesday

    Siting Committee Meeting March 9, 1999

    Present:

    Duncan Agnew, SIO
    John Galetzka, SCIGN Network Coordinator
    Nancy King, USGS
    Frank Webb, JPL

    Proposed New Sites

    A Second Look at Previously Rejected Sites

    Final Approval on CSST

    Challenger Middle School (CHMS) and Lake Los Angeles School (LLAS)

    GOLD and the Eastern California Shear Zone

    John Galetzka's Report


    March 11, 1999
    Thursday

    Tania Gonzalez was not able to attend the ECI monthly meeting yesterday, so Nancy and Frank were not able to talk to her about CHMS at that time (as agreed at yesterday's Siting Committee meeting). However, they did mention the issue to Eldon. Today, Nancy and Tania had a phone conversation. Tania said that she and Eldon will visit CHMS next week to look at the crack and try to determine its origin. Tania also pointed out that the population growth in the Antelope Valley may cause groundwater pumping, and hence subsidence, to increase in the future.

    Fremont High School (FRHS), although permitted, fell off the sled after a new principal proved inhospitable. John is confident that a replacement can be found nearby.

    Site code changes:


    March 30, 1999
    Tuesday

    Since the last entry:

    Reconnaissance and Permitting

    The SCIGN Annual Meeting

    Last Chance to Influence Siting Decisions!


    March 31, 1999
    Wednesday

    More "Last Chance to Influence Siting Decisions" Responses

    Permitting


    April 02, 1999
    Friday

    John Galetzka reports that, due to lack of cooperation in permitting, he is going to propose that the Siting Committee drop Temple City High School (TCHS).

    John also reports that he and Bob Packard propose replacing Elysian Park (EYPK) with Silverlake Reservoir (SILK). The problem at EYPK is also permitting.

    Nancy King will be on vacation April 5 through 9. The next Siting Committee meeting is scheduled for the morning of April 13.


    May 20, 1999
    Thursday

    Siting Committee Meeting April 27, 1999

    Present:

    Duncan Agnew, SIO
    John Galetzka, SCIGN Network Coordinator
    Nancy King, USGS
    Frank Webb, JPL

    1. Report from John Galetzka

    2. Suggestions from CB Members and Others


    June 4, 1999
    Friday

    At a recent meeting of the SCIGN Coordinating Board, the Siting Committee presented a list of 208 stations. The Board voted to accepted these sites. The Siting Committee has now finished its work. The SCIGN Executive Committee and the Network Coordinator (John Galetzka) will decide what to do if any of these sites need to be replaced or dropped.

    Bye!


    Top of this log

    Recon Notes (home page for site recon WWW site)

    SCIGN home page